All projects

Duplication of Highway SP-333 | Bridge over the Tietê River

2025, Borborema - São Paulo
Location
Brasil
Typology
Bridges
Technological Solution

Description

Integrated into the SP-333 highway duplication project - one of the main logistics corridors between northern Paraná and the interior of São Paulo - this undertaking includes the construction of a new bridge over the Tietê River.

With a total length of 2.4 km, the structure features a central span measuring 125 meters in length and 15 meters in height, supported by 56 piers. The project involves the installation of 200 precast beams, each weighing approximately 75 tons.

The beams are being manufactured at a yard set up next to the bridge, and their assembly will be carried out using the BL50 Launcher, developed by ConstruGomes. This equipment enables all phases of the launching operation - from hoisting to final positioning - to be performed safely, efficiently, and accurately.

Technical Solution

BL50 Launcher for precast beams

Technical Features

Total length | 2,400.00 m
Central span length | 125.00 m
Central span height | 15.00 m
Number of piers | 56
Total number of beams | 200
Approximate weight of each beam | 75 tons