For the construction of these two decks, we used BERD's technological solution, the M38-I Movable Scaffolding System (MSS).
The project was developed by ConstruGomes for the consortium Bauarge A6 West, consisting of the companies Hochtief and Bunte.
ConstruGomes is responsible for the execution, operation, and installation of the formwork. We are also responsible for the concrete pour and the finishing works. The several elements that are part of this pivotal project are 44 foundations, 88 piers, 66 provisional piers, 44 crossbeams, and two prestressed double-ribbed decks.