During the state visit, ConstruGomes proceeded to the footings 1stconcreting phase, on the Chaco’i side. This superstructure, supported on 30 piles with 2 meters in diameter and 48 meters deep, will use 3000 cubic meters of concrete and 251 tons of reinforced steel.
ConstruGomes is responsible for the execution of the cable stayed bridge section with 603 meters of length and for the supply of two pairs of FT6 Form Travellers for its execution.