Talbrücke Langer Grund is part of the construction of a new section of the A44 highway that will connect Herleshausen to Kassel.
This project's goal is to improve the connection between these regions on a national and international level.
ConstruGomes is responsible for the operation, handling, and installation of the formwork, for the concrete pour, and for the finishing works. The construction of this Viaduct is composed of two decks. The supply of skilled labour in the sectors of Engineering and Health & Safety is also an important part of ConstruGomes’ scope in this project.
Movable scaffolding system M40-I
Full length | 536.00 m
Max. span between piers | 40.00 m
Pier max. height | 20.00 m
Width | 17.00 m
No. of spans | 14